Project Profile:
  • upgrade of Runway 2 by replacing pavement slabs;
  • reconstruction of the existing apron to accommodate target aircraft types, and construction of a new apron (including lighting and aircraft maintenance installations and de-icing platforms);
  • expansion of safety shoulders and bringing them into compliance with ICAO standards;
  • construction of a new connecting taxiway between Runway 1 and Runway 2;
  • modernization of taxiway lighting installations;
  • rebuilding of the drainage system;
  • building of surface runoff treatment facilities;
  • upgrade of the airport’s power supply system and internal road network, including the patrol road.