TSM to build Bobrov bypass

12/11/18  

TransStroyMekhanizatsiya (TSM), a Mostotrest PJSC subsidiary, will build the Southeast Bobrov Bypass in the Bobrov Municipal District of the Voronezh Region. TSM was awarded the contract as the winner of the corresponding e-auction. The project customer is the Voronezh Region Transport and Road Department. The contract amount is RUB5.1 billion (including VAT). The deadline for completion is October 2021.

As part of the contract, TSM will build a new two-lane Category 2 road with a length of 9.4 km, a bridge across the Bityug River with a length of 237.55 m (at km 3 km of the new road), two overpasses (at km 2 and km 9 of the road), as well as rearrange utility, telecommunication and power transmission lines, water supply networks and surface gas pipelines, build a cattle passageway with a length of 29.10 linear meters (at km 6 of the road), install noise screens, barrier fences and road signs, and make road surface markings.

January 22nd and Avdeev streets, Bobrov's main transport arteries, are currently saturated, especially in summer, due to heavy transit traffic. High traffic intensity leads to rapid road surface deterioration and air pollution, while associated vibration afflicts nearby buildings and their occupants. A steep uphill climb under the existing railway bridge is challenging for some trucks, which creates additional congestion. The new road will take heavy traffic out of central Bobrov, improve the town’s overall transport situation and help preserve its historical part.

The project will be implemented within the framework of the Voronezh Region Government Program «Transport System Development» (Subprogram «Development of the Voronezh Region Road Sector»).

TSM currently has deployed capacity in the Voronezh region, where the company is building the four-lane Losevo and Pavlovsk Bypass at km 633 – km 715 of the M-4 «Don» Highway. Earlier, in November 2013, the company completed construction of the Northeast Voronezh Bypass (km 492 – km 517), and, in November 2016, the Novaya Usman and Rogachevka Bypass (km 517 – km 544).

FOR REFERENCE

TransStroyMekhanizatsiya (TSM) is a subsidiary of Mostotrest PJSC. TSM specializes in construction and reconstruction of transport infrastructure, such as highways and airports. The company operates in the Central, Southern and Far Eastern federal districts, is the main contractor for the construction of segments of the Moscow – St. Petersburg Toll Highway and reconstruction of the M-11 «Narva» Highway; is rebuilding the Moscow Sheremetyevo, Ufa, Rostov-on-Don, Nizhny Novgorod, Khabarovsk and Norilsk airports, and participates in construction and reconstruction of the M-4 «Don», M-9 «Baltiya» and M-10 «Rossiya» highways.

Mostotrest PJSC is the largest diversified infrastructure construction company with a footprint across all key and related market segments, and a participant in pioneering public-private partnership projects in Russia. According to the EMBS Group, an independent industry consultancy, Mostotrest 2016 share of the Russian transport infrastructure construction market was 14.6%.

The Mostotrest Group core business segments include construction and reconstruction of bridges (including road, railway and city bridges), roads and other transport infrastructure, as well as road maintenance, repair and operation services. In 2012, Mostotrest also diversified into road concession management.

The company was founded in 1930 for the construction of off-gauge and large bridges.

Currently, Mostotrest is involved in the implementation of a number of complex integrated transport infrastructure projects, such as construction of several segments of the M-11 Moscow - St. Petersburg Highway, construction and reconstruction of segments of the M-4 «Don» Highway, as well as construction of the Kerch Strait Bridge.

For more detailed information about Mostotrest please visit: www.mostotrest.ru